Beijingxing Energy Network has reported that on October 24, China Power Construction and Power Construction New Power Company issued a notice on the EPC general contracting bidding for the 600,000 kilowatt photovoltaic + 600,000 kilowatts of energy in Fukang City, Xinjiang.

The notice shows that the scale of the project is 600,000 kilowatt photovoltaic + 600,000 kilowatts of energy storage. This project has a 4-hour installation energy storage system based on 25% of the photovoltaic installation capacity, with a capacity of 150MW/600MWh. A new 220kV pressure upgrade station and 3Sugar baby 5kV energy storage stations were built in the venue. A total of 60 2.5MW PCS pre-made tanks and 120 5MWh battery pre-made tanks were arranged in the energy storage stations. The bidding scope includes photovoltaic area, pressure lifting station, energy storage station, opening and closing station, etc.

Notice and notice request that the bidder has had a total contracting project of EPC for photovoltaic power generation engineering over 100MW in the past five years.

The original text is as follows:

China Power Construction New Power Company, Xinjiang, 600,000 kilowatt photovoltaic + 600,000 kilowatts of energy-energy project, Xinjiang

1. Bidding conditions

This bidding project, Xinjiang, 600,000 kilowatt photovoltaic + 600,000 kilowatts of energy-energy project, Xinjiang, 600,000 kilowatt photovoltaic + 600,000 kilowatts of energy-energy project

1. Bidding conditions

This bidding project, Xinjiang, 600,000 kilowatt photovoltaic + 600,000 kilowatts of energy-energy project, Xinjiang, 600,000 kilowatts of energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy-energy The kilowatt-time energy storage project has been approved by the Changji Prefecture Development and Renovation Committee with the registration and preparation case certificate for the Changji Hui Autonomous Prefecture Enterprise Investment Project (Changzhou Development and Reform No. 105). The project owner is China Power Construction (Fukang) New Power Co., Ltd., with a construction fund investment ratio of 20%, and the bank loan is 80%. The bidder is China Power Construction (Fukang) New Power Co., Ltd. The construction funds have been implemented and the project has already met the bidding conditions. Public bidding is now being made for the EPC general contracting of the project.

2. Project Overview and Tendering Scope

2.1 Construction Location

The project is located in Fukang City, Changji Hui Autonomous Prefecture, Weiwu Autonomous Region, Xinjiang. The total amount of the project is about 20201 yuan. The center of the site is 44.2Escort429° East and 88.2876°, and the straight distance from Fukang City Urban Area is about 27km. ConfrontationEscortInternational communication is more convenient and has better construction conditions.

2.2 Project Overview

The total machine size of the project is 600,000 kilowatt photovoltaic + 600,000, she stood up and walked down the stage. Energy storage at kilowatts, this project is set up with a capacity of 25% of the photovoltaic assembly capacity, with a capacity of 150MW/600MWh in 4 hours. A total of 1204224 blocks of 655Wp single crystal silicon photovoltaic components were installed in the venue, 192 3.125MW photovoltaic generator units were built, and 22 new Sugar baby0kV pressure upgrade stations and 35kV energy storage stations were built. A total of 60 2.5MW Sugar daddyPCS pre-made packaging and 120 5MWSugar daddyPCS pre-made packaging and 120 5MWSugar daddyh battery pre-made, etc.

2.3 Planning Period

The daily date of the plan starts the task: based on the start order provided by the supervision;

The daily date of the first batch of photovoltaic array power generation: December 30, 2022;

The daily date of the plan full capacity and network power generation: July 30, 2023;

The daily date of the plan transfer and production: August 30, 2023;

The daily date of the plan completion: December 30, 2023.

The specific situation is based on the actual working time on site.

2.4 Tender Scope

EPC General Contracting Scope for this ProjectSugar baby covers the construction design, completion drawing and design related services for photovoltaic field areas and lifting stations, energy storage stations, and energy storage stations (excluding delivery lines) from design to construction and construction to completion and inspection; All equipment and data purchases except photovoltaic components and energy storage; all responsibility and obligations related to transportation of all equipment and data (except photovoltaic components and energy storage), unloading, storage and storage, storage, secondary reversal, and governance; entry pathSugar baby construction; preparation and construction of all projects in photovoltaic areas and photovoltaic lifting stations and energy storage station departments; installation and adjustment of all equipment in this projectSugar daddy trial; various specialized work and subsequent and process management; handover and service design, procurement and construction tasks, network-related management; all permanent land and temporary land acquisition tasks of the project; and other tasks (excluding delivery and collection projects) that should be completed to achieve the investment target as a whole (excluding delivery and collection projects).

3. Investor qualification request

3.1 The investor shall have the qualification conditions, talents and credibility to undertake the general contracting of this project.

3.1.1 Qualification request: The bidder must have the qualification of an independent legal person of the People’s Republic of China; the registered capital is no less than 120 million yuan; have a completed quality assurance system, and pass the quality governance system certification and environmental governance system The contractor shall have the qualification of the comprehensive A-level engineering exploration and the comprehensive A-level engineering design, and at the same time, the principal of the general contracting of power engineering construction, or the general contracting of water conservancy and hydropower engineering construction cannot leave the seat. “Contract first-level and above qualifications.

3.1.2 Reputation on Credit: The Administration for Industry and Commerce is not listed in the “National Enterprise Trust Information Disclosure System” (.Sugar daddycn) and the Supreme People’s Court uses the “Creditative China” website (.cn) or other prestige. href=”https://philippines-sugar.net/”>Sugar daddyWebpage screenshots of the list of letter executioners in the information sharing platform. Inquiry screenshots of the inquiry bidder and his legal representative, appointed project manager, and design responsible persons in the past three years that the Chinese Judicial Document Network has inquired.

3.1.3Manila escort‘s business results: The bidder has had a total contracting project of more than 100 MW of photovoltaic power generation engineering EPC in the past five years (January 2017-present). The business certificate data contains corresponding winning notice or contractConfirmation book, project acceptance certificate issued by the client (or project completion acceptance certificate or completion certificate), etc. Please provide information on the contract signing time, the contract entity, the scope of service and the contract total amount.

3.1.4 Financial request: Provide financial accounting reports that are recognized in the past three years of conference planning. The financial accounting report includes asset debt statements, cash flow statements, profit statements and financial situation descriptions. In the past three years, it refers to 2019, 2020 and 2021. If the bidder is established for less than the specified year, it shall be provided with the financial status statement since its establishment.

3.1.5 Qualification requirements for project manager: Have a senior engineer or above technical position, have a first-class registered construction engineer qualification, have Ping An qualification certificate (Certificate B), and have served as a manager of one or more photovoltaic (risk) engineering project.

Qualification requirements for project design responsible person: Have a senior engineer or above technical position, and have served as the chief engineer or deputy chief engineer for one or more photovoltaic (risk) projects.

Qualification requirements for project construction responsible person: have an engineer or above technical position, second-level or above registered construction engineer qualification, Ping An qualification certificate (Certificate B), and have se TC: